A manpower allocation problem with layout considerations / Zeppetella, Luca; Gebennini, Elisa; Grassi, Andrea; Rimini, Bianca. - In: ...SUMMER SCHOOL FRANCESCO TURCO. PROCEEDINGS. - ISSN 2283-8996. - ELETTRONICO. - 2014-:(2014), pp. 132-137. ( 19th Summer School Francesco Turco 2014 Senigallia (AN) 09 - 12 September, 2014).
Abstract:
In this study we investigate the problem of assigning tasks to operators in a facility characterized by longitudinal parallel
machines such as in a shop floor served by an overhead travelling crane. Given a master production schedule
(MPS) the objective is to assign all the jobs scheduled on the machines (i.e., the tasks) to the operators in order to
fill to capacity the available workforce minimizing the distance between operators and tasks. In the model we assume
that one task, i.e., a particular production job processed by a particular machine, must be entirely completed by a
single operator. Different levels of automation of the machines are considered, from manual machines that require a
permanent employee to highly-automated machines where a single operator can oversee several machines. During the
setup time or repair time of a machine the operator is considered free to operate on the remaining tasks assigned to
him, if any.
On the basis of the MPS the number of operators is pre-defined in the long-term planning horizon taking in consideration
a fixed mean transfer time between the tasks, that are the different production jobs on different machines. This
value has a huge uncertainty because it is highly influenced by the tasks allocation. In fact a simultaneous multiple allocation
means a continuous back and forth of the operator between his assigned machines. The objective of the model
is the maximization of the operators utilization through minimizing the operator-task distances. The backlogged work
is not admitted, therefore each day is independent of the other days, so a daily staffing is modelled.
The study arises from a specific real-world problem but it could be easily extended to other contexts in which the
operator-task allocation is subject to spatial-layout considerations. In general, non-optimized operators’ travel times
may result in production losses, i.e., machine blocking and work in progress.
Tipologia CRIS:
Relazione in Atti di Convegno
Keywords:
Personnel scheduling, Manpower allocation, Manufacturing, Production
Elenco autori: